Hellertown Curb Ramps Will Soon Be Completed

A Hellertown curb ramp replacement project that was supposed to be wrapped up weeks ago should be completed this week, engineer Bryan Smith of Barry Isett and Associates told borough council Monday night.

Hellertown Borough Hall (FILE PHOTO)
Hellertown Borough Hall (FILE PHOTO)

Smith said that as of Monday, three sidewalk ramps still needed to be completed.

The project was drawn out because some of the handicapped-accessible ramps were not initially completed to Americans With Disabilites Act (ADA) specifications and had to be redone, zoning and codes enforcement officer Kris Russo confirmed.

ā€œThe sidewalk pads that had been marked out with yellow spray paint failed and were not accepted,ā€ Russo said in an email after speaking with Smith.Ā ā€œThe contractor had to remove and replace (them) at his own cost.ā€

Russo explained that ā€œthe unaccepted areas failed because of either quality of workmanship or conformance to the plans.ā€

ā€œADA ramps are extremely hard to install and have a low margin of tolerance, so if the ramp slope does not meet the standards, it fails,ā€ he said.

Russo said a total of 13 ramps have been or are being installed along Water Street and New York Avenue between Northampton and Depot streets as part of the project.

Author
Josh Popichak

Josh Popichak is a veteran local journalist with an extensive background in print and digital news. A Bethlehem native, he has a Bachelor’s degree in history and has maintained a lifelong affinity for the subject. He founded Saucon Source to fill a need for independent local journalism, which has thrived with the support of an engaged, enthusiastic readership. He thanks the community, whose continued support makes this site possible.